Wednesday, May 21, 2008

Update

Construction and IT progress meeting continue. The AV installation date of August 1st is the drop dead date. Further discussion continues on whether if this date is not met the project completion date for the start of fall semester 08 could be delayed.

- The conduit path is moving forward for review and duration by the contractor.

- The MDF and IDF have completed flooring, painted walls and AC unit mounted in the room.

- Cabling installation for data and voice continue through the building.