Construction and IT progress meeting continue. The AV installation date of August 1st is the drop dead date. Further discussion continues on whether or if this date is not met the project completion date for the start of fall semester 08 could be delayed.
The conduit path is moving for review and duration by the contractor. A walkthrough with the contractor for the conduit path is scheduled for Friday May 8, 2008.
The cabling for voice and data begins May 12, 2008. This has caused a slight delay in starting due to the IT move project.